Westminster Bridge Road railway bridge works: information for residents

Westminster Bridge Road passing beneath the railway bridge near Waterloo

Photo: Oxyman / Wikimedia Commons, CC BY-SA 2.0

Major refurbishment planned from 4 January to 29 October 2027

Dear residents,

I am writing to share information about Network Rail’s planned refurbishment of the railway bridge over Westminster Bridge Road, near Upper Marsh and Carlisle Lane.

These works concern the railway bridge near Waterloo station, rather than Westminster Bridge over the Thames.

I attended the stakeholder meeting and a subsequent site visit with the project team to discuss the proposals and raise concerns about noise, traffic, accessibility and the impact on local businesses.

Why are the works needed?

Network Rail describes the bridge as life-expired and says refurbishment is needed to protect the reliability of the Waterloo–Clapham Junction railway corridor and avoid more extensive reconstruction or emergency intervention.

The programme includes repairs to structural steelwork, preparation and repainting of the bridge’s underside, and bird deterrent measures.

When will the works take place?

The main road-related programme is planned for 4 January–29 October 2027.

Planned dates Activity
4–8 January Removal of traffic islands
11–22 January Scaffolding installation
25 January–1 October Bridge preparation, painting and structural works, including changing the scaffolding arrangement
4–15 October Scaffolding removal
18–29 October Reinstatement of traffic islands

The presentation also identifies separate railway possession activities during November and December 2026. These sit outside the main road traffic-management programme.

Network Rail says it has reduced the core programme from 52 to 40 weeks through overlapping activities and round-the-clock weekday working. The January start is intended to follow completion of the Lambeth Road bridge traffic arrangements.

What will change on the roads?

Two of the four traffic lanes on Westminster Bridge Road are expected to close throughout the main scheme. Traffic will continue in both directions, using the remaining carriageway.

The plans also include:

  • Closure of the Station Approach Road connection, with a signed diversion.
  • Suspension and temporary relocation of bus stops affected by the works.
  • Temporary loss of part of the bus lane beneath the bridge.
  • Changes to pedestrian crossings and traffic signals.
  • Additional overnight traffic controls for work on the bridge’s central section, planned between 10pm and 6am.

Please allow additional time when travelling through the area and follow temporary signs. Final temporary bus-stop locations still need to be communicated.

Walking, cycling and accessibility

Network Rail says pedestrian access beneath the bridge will be maintained, with one pavement closed at a time and pedestrians directed to the available route.

Existing cycle lanes on Westminster Bridge Road are intended to remain available. However, the Upper Marsh cycle connection remains subject to detailed arrangements. Earlier proposals identified a closure of four to six weeks; subsequent correspondence proposes separate pedestrian and cycle routes beneath the scaffolding to retain access for more of the programme.

I have requested clearer information about step-free access, wheelchair and mobility scooter access, arrangements for people with visual impairments, and measures to prevent motorcycle incursions into pedestrian routes.

Noise and working hours

The project is planned to operate 24 hours a day, Monday to Friday. Network Rail intends to schedule noisy activities within 8am–5pm wherever possible, but this cannot always be achieved during weekend railway closures.

The following weekends have been identified for extended railway working:

  • 16–17, 23–24 and 30–31 January 2027
  • 6–7 and 27–28 February 2027
  • 20–21 March 2027

These working periods may include overnight activity. Detailed start and finish times and any implications for train services should be confirmed separately.

Scaffolding will be enclosed to contain dust and reduce noise. Generators and other equipment will have additional noise screening. These measures will reduce disturbance but will not eliminate it.

Network Rail has committed to independent noise monitoring, with results shared with Lambeth Council and available on request. I have also asked for clearer advance notification of particularly disruptive activities and publication of monitoring summaries.

Access for residents and businesses

Network Rail says vehicle and pedestrian access will be maintained and construction deliveries will be supervised.

I have asked for further reassurance about emergency access, loading and servicing, accessible routes and how problems will be resolved quickly. Businesses experiencing difficulties should report them promptly so that the project team can investigate.

Keeping residents informed

Network Rail plans to provide letters, monthly stakeholder updates and a community drop-in session in mid-December 2026. The correspondence reviewed does not yet confirm the session’s date, time or venue.

I have requested regular stakeholder review meetings, active monitoring of congestion and clearer arrangements for responding to excessive noise or access problems.

How to raise a concern

For questions or complaints about the railway works, contact Network Rail’s 24-hour helpline: 03457 11 41 41, or use the options on its contact page.

Please identify the project as “Westminster Bridge Road railway bridge refurbishment” and provide the location, date, time and nature of the issue.

You can also contact me at [email protected] if you need help raising a concern or following up a response.

These are important infrastructure repairs, but residents and businesses need clear information, safe access and effective action when problems arise. I will continue pressing for these throughout the project.

Best wishes,
Cllr Ibrahim Dogus
Waterloo & South Bank Ward

Information based on the project correspondence and plans supplied in October 2026. Dates and detailed arrangements may change.